Motorists advised of A58 and A580 lane and road closures

Motorists who use the A58 Stanley Bank Way/Liverpool Road and A580 East Lancs Road are advised that a number of lane and overnight road closures will be in place over the coming weeks.
The closures will be in place until the end of November to allow gas, electricity, Virgin Media, and BT diversion works to be carried out as part of the A58/A580 Pewfall Junction Improvement scheme.
The work is subject to weather conditions, particularly sensitive due to traffic management installation – and road users are advised to take alternative routes where possible, and allow extra journey time.
Access to properties and businesses will be maintained at all times.
Pedestrian access will be maintained, however a suitably signed diversion of the existing pathway will be installed around the construction works if needed.
Details of next week’s closures are outlined in the table below, and traffic management updates will be provided on a weekly basis.
 

Date

 

 

Traffic Management

 

 

 Contractor

 

 

Duration

 

 

 Comment

 

 

23-29/09/19 ongoing

 

 

A580 westbound lane 1 (east of junction)

 

 

Cadent – MP Gas diversion

 

 

Full time

 

 

Last completion date given by Cadent was 3rd Oct

 

 

23-24/09/19

 

 

A580 westbound lane 1 (west of junction)

 

 

ENWL – Electric diversion

 

 

Installed at 09:30 – remain on full time until switch

 

 

Cabling pulling, jointing and backfilling

 

 

23-24/09/19

 

 

A580 eastbound lane 1 (west of junction)

 

 

ENWL – Electric diversion

 

 

Installed at 09:30 – remain on full time until switch

 

 

Cabling pulling, jointing and backfilling

 

 

23-24/09/19

 

 

Liverpool Rd – priority TM outside property 297

 

 

BT – ducting diversion works

 

 

Installed from 07:00, remain on full time until switch

 

 

 

 

 

23/09/19

 

 

Install temporary 4 way lights on A580 / A50 junction

 

 

BT – ducting diversion works

 

 

Installed Monday 23rd Sept after 19:00, remain on until switch

 

 

Siemens to attend site to bag and turn off

 

 

23-25/09/19

 

 

A58 Stanley Bank Way – southbound lane closed

 

 

BT – ducting diversion works

 

 

Installed Monday 23rd Sept after 19:00, remain on until switch

 

 

25-26/09/19

 

 

A58 Stanley Bank Way – north bound straight on and right hand filter lane closed

 

 

BT – ducting diversion works

 

 

Installed at 09:30 – remain on full time until switch

 

 

 

 

 

27/09/19

 

 

A58 Stanley Bank Way – left hand filter lane closed with diversion

 

 

BT – ducting diversion works

 

 

Installed at 09:30 – remain on full time until switch

 

 

 

 